Why Is the Boeing 777X Still Not Flying Passengers?

Boeing’s 777X is the largest twin-engine jet ever built. It’s meant to replace the ageing 777-300ER and, for several airlines, the Airbus A380, and it was supposed to enter service in 2020. As of Boeing’s latest update, certification and first delivery are now aimed at 2027. That’s not a small slip. It’s roughly seven years, and it has cost the programme an estimated $15 billion in overruns. The reasons are specific, and most of them lie outside the aircraft’s own design.

The Boeing 777X at its 2019 roll-out event in Everett, Washington
The 777X at its March 2019 roll-out — over six years before its now-targeted certification date. Photo: Dan Nevill — CC BY 2.0

Animated

Promised for 2020, still waiting: the 777X timeline

20132015201720192021202320252027promised: 2020LaunchedDubai AirshowRoll-outMarch 2019First flightJanuary 2020Thrust-link crackTests paused, Aug 2023GE9X mid-sealCrack found Jan 2026Now targetedCertification, 2027YEAR 2013on scheduleFAA CERTIFICATION QUEUE737 MAX 7737 MAX 10777-9FAA desk →

The dashed flag is where the 777-9 was supposed to enter service. Each red marker is a problem that pushed it back, and the counter shows how far past the promised date the programme has run. Below: the FAA certifies Boeing’s jets one after another, and the 777X sits behind the 737 MAX 7 and MAX 10. Schematic; event placement within a year is approximate.

The FAA queue, not just the aircraft

The biggest single factor isn’t a flaw in the 777X design. It’s the aircraft’s place in the FAA’s certification queue. The back-to-back 737 MAX accidents of 2018-19 permanently changed how closely the FAA checks Boeing’s certification work. That closer scrutiny has badly and repeatedly delayed the certification of the MAX 7 and MAX 10 variants. FAA Administrator Bryan Bedford has said 777X certification comes after the MAX 7 and MAX 10 work. So the 777X isn’t only waiting on its own process; it’s waiting behind other aircraft.

Animated

The 777-9’s moving goalposts

2019202020212022202320242025202620272028first flight, Jan 2020As of 2013 launch: first delivery target 2020the target keeps moving →

Each time Boeing updated the 777-9 schedule, the first delivery moved further out: from 2020, when the programme launched in 2013, to 2027 as of Boeing’s October 2025 update. The aircraft itself first flew on 25 January 2020; the delays are about certification and engine issues, not about getting it into the air. Dates as publicly announced.

The engine problem that actually blocks the routes it’s built for

Separately, the GE9X engine, the largest jet engine ever built, made by GE Aerospace for the 777X, has had two real technical problems. First came a fatigue problem with a thrust link. More recently there’s been a durability problem with a part called the “mid-seal”. That second one matters more than it sounds, because it holds up ETOPS certification, the approval that lets a twin-engine aircraft fly long routes far from a diversion airport. The 777X is a long-haul twin built for exactly those routes. Without ETOPS approval it can’t do the job it was designed for, however well the rest of the aircraft performs.

The real numbers

The 777X program, in real numbers

2020

Original service-entry target

First set before the program's first delay

2027

Current certification target

Per Boeing's October 2025 update

~$15B

Program overruns to date

Cost of delays and rework since program launch

7

Major airlines waiting

Emirates, ANA, BA, Cathay Pacific, Lufthansa, Qatar, Singapore Airlines

What airlines are doing while they wait

Airlines that ordered the 777-9 as their long-haul flagship, including Emirates, All Nippon Airways, British Airways, Cathay Pacific, Lufthansa, Qatar Airways and Singapore Airlines, couldn’t simply sit and wait. Each has had to keep older widebodies such as 777-300ERs, Airbus A380s and Boeing 747-400s flying well past their planned retirement. That means paying the higher maintenance and fuel costs of older aircraft for longer than intended. Spread across every airline in the queue, it’s probably the least visible part of the 777X story, and one of the most expensive.

The wing that folds: why the 777X needs special rules

Part of what makes certification slow is that the 777X does something no airliner did before. Its wingtips fold.

A longer wing produces lift more efficiently, because less energy is lost in the swirling vortices at each tip. Boeing wanted that efficiency, so the 777-9’s wingspan is 71.8 metres in flight.

Airports set gate sizes by wingspan, though, and a 71.8-metre wing would need the biggest gates, the ones built for the A380 and 747. So on the ground, about 3.5 metres of each tip hinges upward, bringing the span to 64.8 metres. That fits the same gates as today’s 777.

The regulators had no existing rules for a moving wingtip on a passenger jet. So in May 2018 the FAA published special conditions just for it. Boeing must show that a wingtip coming unlocked is extremely improbable and can’t result from any single failure. The crew must get more than one independent alert if the tips aren’t locked for takeoff, and the takeoff warning system has to sound if they try. Every new idea like this adds tests to the certification queue.

Common Questions

Frequently Asked Questions

When was the 777X originally supposed to enter service?

2020. As of Boeing’s October 2025 update, certification and first delivery are now aimed at 2027, which puts the programme roughly seven years behind its original schedule.

Is the delay mainly about the aircraft itself, or something else?

Both, but the biggest single factor is the order of the FAA’s work. The FAA’s own leaders have said 777X certification comes after the 737 MAX 7 and MAX 10 in the queue. That’s a direct, lasting result of the closer scrutiny the agency has applied to Boeing since the 2018-19 MAX accidents.

What specifically is wrong with the GE9X engine?

A durability problem with a part of the engine called the “mid-seal”, which followed an earlier fatigue problem with a thrust link. The mid-seal problem specifically affects the aircraft’s ETOPS approval. That’s the certification that lets a twin-engine jet fly long routes far from a diversion airport, exactly the routes the 777X is built for.

Which airlines are most affected by the delay?

Emirates (the biggest customer), ANA, British Airways, Cathay Pacific, Lufthansa, Qatar Airways and Singapore Airlines all planned the 777-9 as a centrepiece of their long-haul fleets. To cover the gap, they’ve had to keep older 777-300ERs, A380s and 747-400s flying for longer.